Hello all,
We wanted to share some gas line work that is expected to occur in third quarter of 2020 so residents in those general areas are well informed. Here is a link to a detailed PDF on the work that is scheduled:
Here is the message received from NiSource:
Hi Clintonville leadership,
Hope everyone is doing well and enjoying the holiday season.
Just wanted to catch everyone before the holidays, as we just received our planned 2020 work.
With the current Pacemont & Calumet project fresh in everyone’s minds, we will have one 2020 project in Clintonville entitled Rathbone & Milton. This project will be the same exact type project where we will be upgrading the gas line system and communicating with customers impacted.
This will take place (tentatively) in the 3rd Quarter (think late summer, early fall). We will install about 6,344 feet of mainline pipe and replace 156 service lines. In comparison to Pacemont and Calumet, which installed 6,100 feet of mainline pipe and impacted 227 customers.
Obviously when we have a better idea of start date, we will communicate that with you and customers impacted.
As further information is made available, updates will be provided but sharing what has been given in terms of planning at this time.